E.R. Snell Contractor is currently scheduled to start two connected I-20 contracts totaling $8,445,000 to resurface interstate travel lanes in both directions from Exit 93 (Newton) to Exit 113 (Morgan).

Milling operations (current riding layer removal) was set to begin Tuesday night westbound from the Exit 113 end working to Covington. All work is 9 p.m. to 6 a.m. to mitigate delays given 35,000 to 48,000 daily vehicle volumes.

Snell’s subcontractor, Miller Group, plans to mill seven days a week. Milling surfaces are required to sit at least 48 hours before covering, so drivers will see uneven surfaces during the project.

Due to temperature requirements, paving operations should likely end in late October and pick back up in spring 2022.

This project is replacing the current Open Graded Friction Course (OGFC) with new. Benefits of OGFC as a thin, permeable asphalt layer include roadway friction and less water buildup as rain drains through the material and off the roadway.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.